Paragon Energy Networks provided a full HV infrastructure upgrade at a major industrial park in Livingston. The project involved the decommissioning of ageing assets and the installation of a new 33kV substation to support ongoing site expansion and increased electrical demand.
Design and build of new 33kV substation
Removal of outdated electrical infrastructure
Installation of HV protection equipment and cabling
Full integration and commissioning of new systems
Live site environment with operational facilities
Managing outage windows with minimal downtime
Detailed interface with DNO for technical acceptance and final connection
We implemented a staged delivery strategy, allowing site operations to continue without interruption. Detailed outage planning and early engagement with the DNO enabled us to minimise power-down periods. Our project team handled all technical submissions and on-site commissioning, ensuring a seamless transition from legacy systems to upgraded infrastructure.
Copyright © 2025 Paragon Energy Networks Ltd. All Rights Reserved. This website, including its design, text, graphics, logos, and other original content, is the exclusive property of Paragon Energy Networks unless otherwise stated. All materials are protected by copyright, trademark, and other intellectual property laws.