Paragon Energy Networks delivered a complete 11kV new connection to support a mixed-use development consisting of retail, office, and residential units in Stirling. As the ICP, we led the entire process from network design to final energisation.
11kV network design and route planning
Trenching, duct installation, and HV cable laying
Installation of ring main unit (RMU) and metering panels
Final testing, commissioning, and DNO interface
High pedestrian and traffic flow in the area
Tight delivery windows around site milestones
Multi-phase energisation requirements for separate units
Careful scheduling and phased implementation allowed us to work around the active city centre environment. Early collaboration with Stirling Council and the local DNO ensured streamlined approvals and minimal disruptions to traffic and utilities.
Copyright © 2025 Paragon Energy Networks Ltd. All Rights Reserved. This website, including its design, text, graphics, logos, and other original content, is the exclusive property of Paragon Energy Networks unless otherwise stated. All materials are protected by copyright, trademark, and other intellectual property laws.