Paragon Energy Networks was appointed to deliver an 11kV diversion project in Dundee to support a major mixed-use development. The existing HV infrastructure required rerouting to allow for site clearance and new construction, while maintaining network integrity and minimising disruption to the surrounding area.
Survey and assessment of existing HV infrastructure
Full design of new 11kV route and equipment layout
Cable diversion works and substation repositioning
Testing, commissioning, and DNO handover
Maintaining uninterrupted supply to adjacent buildings
Limited working space within a tight urban construction site
Rapid turnaround required to meet planning milestones
We carried out a phased diversion strategy to avoid downtime for nearby businesses and residents. Close collaboration with SP Energy Networks ensured fast-track design approvals and early engagement on technical requirements. Our on-site team coordinated daily with the main contractor to align works with site access and development sequencing, ensuring safe, efficient delivery within the required timeframe.
Copyright © 2025 Paragon Energy Networks Ltd. All Rights Reserved. This website, including its design, text, graphics, logos, and other original content, is the exclusive property of Paragon Energy Networks unless otherwise stated. All materials are protected by copyright, trademark, and other intellectual property laws.